A Head Start final rule removes federal requirements for staff wage scales, specified wage benchmarks and benefits introduced in 2024. The Administration for Children and Families says local programs should decide compensation within their funding and applicable law; commenters warned that removing the provisions could worsen workforce instability.
What is being removed
The rule deletes 45 CFR 1302.90(e) and (f). ACF says this eliminates requirements to develop or update pay scales for all staff, provide education staff wages comparable to public preschool teachers, provide all staff salaries sufficient for basic living costs, and promote wage comparability between Head Start Preschool and Early Head Start. Specified benefit requirements are also removed.
The rescission does not require programs to reverse existing pay increases, ACF says. Programs may choose to maintain or improve compensation. Applicable labor laws and staff qualification requirements remain.
The removed requirements had compliance dates of August 2028 for benefits and August 2031 for wages, according to the rule.
Projected places, not measured enrollment
ACF estimates that, without increased congressional appropriations, implementing the compensation provisions would require cutting approximately 106,000 funded slots. It describes that number as a potential effect on future funded capacity, not a prediction of actual enrollment or classroom operations.
Some commenters argued that workforce shortages were driving closures and that removing compensation requirements would not improve recruitment. ACF acknowledges continuing staffing challenges and says the result depends on workforce availability, local labor markets and funding.
Its approximately $2.1 billion estimate concerns eventual annual transfers associated with avoided future compensation requirements. ACF says this is not a reduction in appropriated Head Start funding. It also acknowledges that programs could seek approval to reduce slots to raise compensation, producing fewer preserved slots than estimated.
When the rule takes effect
The public-inspection copy is scheduled to be published in the Federal Register on November 16, 2026. It is a final rule, but that scheduled publication has not yet occurred.
The PDF's DATES line prints the placeholder “[INSERT DATE 60 DAYS AFTER PUBLICATION IN FEDERAL REGISTER]”. Its effective-dates section repeats the 60-day formula. By this desk's count, 60 days after the scheduled publication is January 15, 2027, a Friday; the Register's document API assigns the same effective date. The PDF itself does not print that completed calendar date. The date depends on publication occurring as scheduled.